Frontex preparation

RCT-2026-00085

Frontex AD9 training

Budget and financial management coordination. Practise the written competency test and interview in English.

These are original practice exercises with answer guides. Use your Frontex invitation for the test format and timing.

Selection process

Official Frontex vacancy

Study guide

Multiannual planning and the annual budget

Translate strategic priorities in the Single Programming Document into activities, outcomes and annual resource needs. Separate the baseline from new requests. Project commitments, payments and staffing by year. Test whether the proposal fits the planned funding and show the obligations it creates for later years.

For each submission, verify its assumptions, unit costs, tender schedule, dependencies and owner. Consolidate competing bids under a common ceiling. Keep an explicit status for projections that still require approval.

Budget execution and forecasting

Compare actual commitments and payments with their respective time-phased plans. Record whether a variance comes from timing, price, volume or a change in scope. Build a year-end forecast from actuals plus expected remaining execution, using delivery and invoice dates.

For each material variance, name the driver, quantify the impact, assign an action owner and agree a review date with Finance. Confirm whether any apparent headroom is available for another purpose before making a recommendation.

Financial rules and internal control

Apply sound financial management by assessing economy, efficiency and effectiveness. Check the budget line, available appropriations, financing decision where applicable, file evidence and the competent authority before any commitment or adjustment. Track changes in the budget and relevant planning records.

Separate the decisions of the authorising function from accounting and payment duties. Escalate material non-compliance, preserve the audit trail and record the control owner and next review. Verify the Agency’s rules and delegations before proposing approval or transfer procedures.

Negotiation and executive briefing

Agree with Finance on a common definition of costs, scope and deadlines. Have divisions rank requests by strategic contribution, delivery readiness, impact of delay and cost over time. Use those criteria to frame choices for the Budget Steering Committee.

Lead a briefing with the decision required and its timing. Give comparable options, budget impact, risks and a recommendation. Identify which body or official must approve the decision and how the outcome will be tracked.

Written practice

Draft a response before opening the answer guide. Copy any draft you want to keep before leaving the page.

Diagnose a payment variance

It is 30 September. The Deputy Executive Director wants to know how much of the apparent underspend is available for new priorities. The approved annual payment budget is €36.0m. The payment plan through September was €18.4m and recorded payments were €15.6m. Finance projects a further €17.6m in payments by December. A separate €2.0m milestone invoice, excluded from that projection, has moved to February. A disputed €1.1m invoice could still become payable in December and is also excluded from the projection.

Draft a 200-word note. Quantify the September variance, base and downside year-end forecasts, and the remaining amount under the annual budget in each scenario. State what must be checked before recommending a reallocation.

Open answer guide
  • September payments are €2.8m below plan, about 15.2% lower. Report this as a payment variance.
  • Base forecast is €33.2m with €2.8m below budget. If the disputed invoice becomes payable, the forecast is €34.3m and the difference falls to €1.7m.
  • The February invoice still affects future-year funding. Ask Finance to confirm the outstanding commitments, latest milestone, applicable carry-over or next-year treatment, restrictions on the funding line and the available authority for any transfer.
  • Recommend a decision date and a named owner to update the forecast once the invoice dispute and revised delivery schedule are confirmed.

Prioritise bids under a three-year ceiling

The Budget Steering Committee has an annual planning ceiling of €24.0m for each of the next three years. The approved baseline and three new bids are set out below. The reporting upgrade meets a fixed compliance deadline. The shared systems renewal is procurement-ready and reduces reliance on a service contract that expires after Year 2. The service expansion is optional and can be phased.

Budget itemYear 1 (€m)Year 2 (€m)Year 3 (€m)
Existing baseline 18.419.119.5
Shared systems renewal 3.83.22.1
Reporting upgrade 1.71.51.5
Service expansion 2.21.81.4

Write an options paper of up to 250 words. Show the effect of funding all bids, propose an affordable package, and explain what you would ask divisions and Finance to validate before approval.

Open answer guide
  • The full package costs €26.1m, €25.6m and €24.5m, exceeding the annual ceilings by €2.1m, €1.6m and €0.5m respectively.
  • Funding the reporting upgrade and systems renewal costs €23.9m, €23.8m and €23.1m including the baseline. The remaining amounts are €0.1m, €0.2m and €0.9m.
  • Explain which deadline or dependency each funded bid protects. Present a costed rephasing option for expansion if it can fit every affected year. Explain the consequences if it is deferred.
  • Ask for the split between commitments and payments, procurement and staffing assumptions, contingency needs and alignment with the Single Programming Document. Name the next decision and its approval route.

Advise on a grant adjustment

A division asks Finance to pay €420,000 on a grant, including €65,000 for additional activity. The original agreement covers the other €355,000. The extra work has started and a draft amendment exists, but the file contains no signed amendment or decision approving the change. The division says the external partner needs a decision before the next reporting cut-off.

Prepare an executive briefing of up to 200 words. State the immediate decision, document checks, escalation path and reporting impact.

Open answer guide
  • Keep the €65,000 disputed amount separate. Ask the responsible authorising function and Finance to verify the applicable grant conditions, budget coverage, eligibility and approval path before committing to payment.
  • Treat the €355,000 separately only if Finance confirms that it can be processed independently and that the original obligations, evidence and checks support payment.
  • Preserve the original agreement, amendment history, evidence of delivery and any communications. Identify who should record the exception and advise on the compliant options.
  • Brief the Deputy Executive Director on the decision required, the deadline, the impact of a delay and how the amounts should be reflected in the forecast pending resolution.

Interview practice

Answer aloud in English. Pick a real example and explain your decision, the part you played and how you measured the outcome.

Tell us about a multiannual plan you revised after a funding or delivery change.

Explain which assumptions changed, how you separated annual and future-year impacts, and which option the decision-maker approved.

Describe how you detected a significant budget variance and prevented a year-end problem.

Give the original baseline and variance. Explain how you verified the cause with Finance, who acted, and what the updated forecast showed.

Give an example of conflicting budget requests you negotiated across teams or countries.

Name the constraints, the criteria you agreed, how you kept stakeholders involved, and what trade-off was accepted.

Describe a time when a senior colleague wanted to proceed before a financial control was complete.

Explain how you raised the issue, recorded the risk, proposed a compliant alternative and protected the delivery objective.

Tell us how you improved the quality of financial reporting for an executive or board.

Describe the original problem, the checks and reporting cadence you implemented, and the measurable improvement in accuracy or speed.